Solar cell plant — installation packages
Lump-sum subcontracts · bid one package or several
Open now — simple pipe racks, in two packages: A (96 racks) and B (94 racks). We supply the racks; you unload, move, assemble, align, bolt and torque them, and cut insulated metal panel (IMP) wall openings. Piping connections are by others.
Opening November 2026 – January 2027, as equipment arrives:
- Main pipe rack steel erection (32 modules)
- Fabric and sheet-metal ductwork
- Process exhaust — hot, silane, FRP and welded organic exhaust
- CDA and N₂ piping, including pressure testing
- Utility plant: chillers, air compressors, cooling towers and PCW skids rigged and set; pumps and piping
- Cooling-tower steel and outdoor pipe racks
- Rooftop air handlers, plenums and ductwork
- Rooftop natural gas piping (welded and threaded)
Crews we need
- Pipefitters & welders (exhaust, gas, CDA/N₂)
- Sheet-metal & duct installers
- Riggers, signal persons & crane operators
- Ironworkers / structural fitters
- Forklift & telehandler operators
- Boom & scissor lift access
- Foreman and site safety lead
Bidder requirements
- Method statement and JHA before work starts
- OSHA training, site induction, daily roster and clock-in
- Verified work authorization (I-9) for all personnel
- CGL, auto, employer's liability, $5M umbrella and rigger's liability